Files
the-other-dude/.planning/STATE.md
Jason Staack 6ccccb3902 docs(11-02): complete frontend site list and detail pages plan
Co-Authored-By: Claude Opus 4.6 (1M context) <noreply@anthropic.com>
2026-03-18 21:48:51 -05:00

2.0 KiB

gsd_state_version, milestone, milestone_name, status, stopped_at, last_updated, progress
gsd_state_version milestone milestone_name status stopped_at last_updated progress
1.0 v9.7 Tower & Site Management unknown Completed 11-02-PLAN.md 2026-03-19T02:47:05Z
total_phases completed_phases total_plans completed_plans
5 0 3 2

Project State

Project Reference

See: .planning/PROJECT.md (updated 2026-03-18)

Core value: Operators can monitor, configure, and troubleshoot their entire MikroTik fleet from a single pane of glass Current focus: Phase 11 — site-data-model-foundation

Current Position

Phase: 11 (site-data-model-foundation) — EXECUTING Plan: 3 of 3

Performance Metrics

Velocity:

  • Total plans completed: 1
  • Average duration: 3 min
  • Total execution time: 0.05 hours

By Phase:

Phase Plans Total Avg/Plan
- - - -

Accumulated Context

| Phase 11 P01 | 3min | 2 tasks | 9 files | | Phase 11 P02 | 6min | 3 tasks | 8 files |

Decisions

Decisions are logged in PROJECT.md Key Decisions table.

  • Sites must use nullable site_id FK (never mandatory) to preserve flat-list workflow
  • Per-client wireless data gets its own NATS stream and hypertable (not DEVICE_EVENTS or wireless_metrics)
  • Link state machine requires 3 consecutive missed polls before marking down (prevents false flapping)
  • [Phase 11]: alert_count set to 0 with TODO -- alert_events integration deferred to avoid coupling
  • [Phase 11]: Site detail page kept minimal (info + stats) -- full dashboard deferred to Phase 14
  • [Phase 11]: Used Dialog for delete confirmation (no AlertDialog component in UI library)

Pending Todos

None yet.

Blockers/Concerns

  • OpenBao dev instance loses Transit keys on data wipe — device creds need re-entry
  • RouterOS 7 WiFi registration-table field names need validation on real hardware (Phase 12)
  • MAC-to-device resolution data source needs codebase audit (Phase 13)

Session Continuity

Last session: 2026-03-19T02:47:05Z Stopped at: Completed 11-02-PLAN.md Resume file: None